Follow
+86 186 1711 2376 peter.sun@serow-tech.com

Capability 05 — Prototype to Production

Six stages, with no undocumented handoffs.

A remote program is a sequence of commitments. At each stage you should know what was decided, what was tested and what it cost to move forward. This page states the sequence and the typical duration of each step.

The sequence

What enters each stage, and what you approve to leave it.

Durations assume a defined protocol, available samples and timely approvals. They are planning ranges, not contractual dates; the committed schedule is issued after the brief review.

Stage 01

Brief and feasibility

We map the control target, protocol, markets, volume and launch window against what is standard, what is custom and what needs a discovery step. The output is a requirement matrix and a gap list.

1–2 weeks · You approve: scope and indicative cost
Stage 02

Concept and design

Key-map drawing, industrial design direction, mechanical architecture, PCB block diagram and firmware architecture. Design reviews include manufacturing engineering so the concept can be built.

3–6 weeks · You approve: design freeze package
Stage 03

Prototype (EVT)

Functional samples with the intended keypad material and radio. Used for key feel, RF range, current draw and firmware behavior. Issues found here are cheap; issues found after tooling are not.

3–5 weeks · You approve: prototype acceptance
Stage 04

Validation (DVT)

Pre-scan, reliability tests and protocol conformance against the agreed plan. A written report states what passed, what failed and what changed as a result.

2–4 weeks · You approve: validation report
Stage 05

Tooling and pilot (PVT)

Molds, keypad tools, assembly fixtures and test fixtures are released. T1 samples confirm fit and finish; the pilot build confirms the process at the target line rate.

4–8 weeks · You approve: golden sample and pilot report
Stage 06

Mass production

Production runs against the released test specification, with lot records and per-unit functional test. Changes after release follow the same revision discipline as the design.

Per order · You receive: lot records and test summary

From pilot to shipment

SMT — boards placed and reflowed before assembly.
01SMT — boards placed and reflowed before assembly.
Assembly line — pilot and mass production run on the same line.
02Assembly line — pilot and mass production run on the same line.
Warehouse — packed units held before despatch.
03Warehouse — packed units held before despatch.

Schedule reality

Most delays are waiting on a decision, not on engineering.

The technical work usually moves at a predictable pace. What stretches a program is an approval that waits two weeks, a device list that changes after validation, or a certification lab with a full calendar.

  • Sample remotes or receivers arrive late
  • Key map changes after the design freeze
  • Protocol document is incomplete at kickoff
  • Certification market list grows mid-program
  • Packaging artwork arrives after the pilot build
  • Approval cycles are longer than the engineering work
Most delays are waiting on a decision, not on engineering.
What we ask for at kickoff
  • A named decision-maker on your side
  • One consolidated device list with regions
  • Samples of every device family
  • Target markets and certification scope
  • Volume, pilot size and launch window
  • Brand assets and packaging direction

Stage gates

What “approved” means at each gate.

GateEvidence reviewedWhat it authorises
G1 — Scope Requirement matrix, gap list, indicative cost Design work and sample procurement
G2 — Design freeze Drawings, BOM, key map, firmware architecture Prototype build and tooling quotes
G3 — Prototype Functional samples and test notes Validation testing
G4 — Validation Signed test report and pre-scan results Tooling release and pilot planning
G5 — Pilot Golden sample and pilot report Mass production
G6 — Production Lot records and test summary Shipment and field support

A gate can be passed with open items only if those items are written down and accepted. “We will fix it in production” is not a gate criterion.:

Questions

Program FAQ

How long does a typical program take end to end?
A configured platform can reach a pilot in roughly 8–12 weeks. A full-custom handset with a new enclosure, keypad tool and certification usually takes 20–30 weeks. Both ranges assume samples and approvals arrive on schedule; the committed plan is issued after the brief review.
Can we skip validation to save time?
We can reduce scope where the risk is genuinely low, for example by reusing an existing platform and its reports. We will not release new tooling without a signed validation report for the items that changed. Skipping the report does not remove the risk, it only moves it to the customer.
Who pays for tooling, and when?
Tooling is normally paid before release, separately from unit price, and is itemised in the quotation. Ownership and amortisation are commercial terms agreed in the development contract. We do not hide tooling in a unit price without saying so.
What happens if the pilot fails?
The pilot report identifies whether the cause is design, fixture, component or process. We fix the cause and repeat the affected stage. A failed pilot does not move to mass production, and the cost of the repeat is scoped against the cause.

Related: Manufacturing Reliability & Hygiene

Start a project

Put a date on the first gate.

Send the device list, target markets and launch window. We will return a scope and a realistic first-stage plan.

Typical reply within one business day